Quick Answer: The cancellation of the Ganeshpur captive coal block by the Supreme Court in Manohar Lal Sharma and the later Coal Mines (Special Provision) Act, 2015 are Change in Law events under Article 10 of the PPA/PSA, so Adhunik Power is entitled to compensation from 25.08.2014 with carrying costs. However, Article 2.5 of the PPA/PSA protects WBSEDCL against higher costs of e-auction or imported coal bought before the cancellation, and APTEL's award of that cost was set aside.
In West Bengal State Electricity Distribution Co. Ltd. v. Adhunik Power & Natural Resource Ltd. & Ors. (2026 INSC 202), the Supreme Court held that the "captive source" in Article 2.5 of the PPA/PSA refers to the Ganeshpur Coal Block, as shown by the Minutes of Meeting dated 03.01.2011 and WBSEDCL's letter dated 30.04.2012 (paras 19–23). The change in interpretation of the CMN Act and the MMDR Act in Manohar Lal Sharma, and the 2015 Act, fall within Articles 10.1.1(b) and 10.1.1(f), and Article 2.5 and Article 10 operate in different fields (para 24). A Bench of Chief Justice Surya Kant, Justice B.V. Nagarathna and Justice Joymalya Bagchi partly allowed the appeals (para 26).
Status: APTEL's common order dated 04.09.2025 set aside to the limited extent it granted compensation for coal procured through e-auction/import to meet the shortfall in tapering linkage pending operationalisation of the coal block; Change in Law compensation from 25.08.2014 with carrying costs upheld; CERC to modify its consequential order dated 11.02.2026 within four weeks; appeals partly allowed (para 26).
Headnote: Coal Block Cancellation as Change in Law
Power Purchase Agreement / Power Supply Agreement – Articles 2.2, 2.5 and 10 – Change in Law – Cancellation of captive coal block in Manohar Lal Sharma v. Principal Secretary – Coal Mines (Special Provision) Act, 2015 – Coal Mines Nationalization Act, 1957 – Mines and Minerals (Development and Regulation) Act, 1957 – Indemnity against coal cost escalation – Tapering linkage – E-auction and imported coal – Interpretation of contract with reference to surrounding circumstances – Indian Evidence Act, 1872 – Sections 91, 92, 94 and 95.
Held: (i) Though the PPA/PSA did not expressly name the captive source, read with the Minutes of Meeting dated 03.01.2011 and the letter dated 30.04.2012 the "captive coal block" in Article 2.5 refers to the Ganeshpur Coal Block in Jharkhand (paras 8–9, 19–21, 23).
(ii) A written contract is ordinarily construed from the document itself, but facts linking its terms to existing facts, or giving meaning to a term that would otherwise be meaningless, may be looked into, as summarised in Anglo American Metallurgical Coal (para 22).
(iii) WBSEDCL, being a party to those correspondences and never having disputed them, cannot contend that the PPA/PSA did not prescribe Ganeshpur as the captive source (para 23).
(iv) The change in interpretation of the CMN Act and the MMDR Act in Manohar Lal Sharma, resulting in cancellation of the coal blocks, and the subsequent Coal Mines (Special Provision) Act, 2015 fall within Articles 10.1.1(b) and 10.1.1(f) of the PPA/PSA (para 24).
(v) Article 2.5 and Article 10 operate in different fields; WBSEDCL cannot claim immunity under Article 2.5 from Change in Law compensation, which APTEL rightly awarded from 25.08.2014 with carrying costs (para 24).
(vi) Before the cancellation, Article 2.5 applied; APTEL erred in holding the indemnity inapplicable because the delay in operationalising the coal block was attributable to the lead miner or the go-no-go policy, and its reliance on GMR Kamalanga was misconceived (para 25).
(paras 19–26)
Case Details: WBSEDCL v. Adhunik Power (2026 INSC 202)
Final Outcome: Appeals partly allowed; APTEL's award of compensation for e-auction/imported coal to meet the shortfall in tapering linkage set aside; compensation for Change in Law events from 25.08.2014 with carrying costs upheld; CERC to modify its consequential order within four weeks; no order as to costs.
Case: West Bengal State Electricity Distribution Co. Ltd. v. Adhunik Power & Natural Resource Ltd. & Ors.
Neutral Citation: 2026 INSC 202
Case No.: Civil Appeal Nos. 2584–2585 of 2026
Court: Supreme Court of India (Civil Appellate Jurisdiction) – Reportable
Date of Decision: 27 February 2026
Bench: Chief Justice Surya Kant, Justice B.V. Nagarathna and Justice Joymalya Bagchi (author)
Relevant Acts & Sections: PPA dated 25.03.2011 and PSA dated 05.01.2011 – Articles 2.2, 2.5 and 10; Coal Mines (Special Provision) Act, 2015; Coal Mines Nationalization Act, 1957; Mines and Minerals (Development and Regulation) Act, 1957; Indian Evidence Act, 1872 – Sections 91, 92, 94 and 95 (Sections 94, 95 and 98 of the Bharatiya Sakshya Adhiniyam, 2023)
Impugned Order: Common order dated 04.09.2025 of the Appellate Tribunal for Electricity in Appeal No. 143 of 2020 and Appeal No. 66 of 2022, modifying CERC's order dated 29.01.2020 in Petition No. 305/MP/2015 (paras 1, 14, 16)
Counsel: Mr. Kapil Sibal, Senior Counsel, for the appellant; Mr. C.A. Sundaram, Senior Counsel, for Respondent No. 1 (paras 17–18)
Source: Supreme Court of India (official website)
Key Holdings of the Supreme Court
- The captive source in Article 2.5 of the PPA/PSA is the Ganeshpur Coal Block, as found concurrently by CERC and APTEL (paras 19–21).
- Surrounding circumstances and correspondence may be used to identify a term that the written contract does not expressly name (paras 22–23).
- Cancellation of the coal block after Manohar Lal Sharma and the Coal Mines (Special Provision) Act, 2015 are Change in Law events under Articles 10.1.1(b) and 10.1.1(f) (para 24).
- Article 2.5 does not shield the procurer from Change in Law compensation, as it operates in a different field from Article 10 (para 24).
- For the period before cancellation on 25.08.2014, the Article 2.5 indemnity applies, and no compensation is payable for e-auction or imported coal bought to meet the tapering linkage shortfall (para 25).
Brief Facts of the Case
On 05.01.2011 WBSEDCL executed a PSA with PTC India Limited for 100 MW of power for 25 years, and on 25.03.2011 PTC executed a back-to-back PPA with Adhunik Power (APNRL). The West Bengal Electricity Regulatory Commission approved them on 15.12.2011 (paras 2–4). The Minutes of Meeting dated 03.01.2011 recorded that APNRL had a captive coal block at Ganeshpur, Jharkhand, in joint venture with Tata Steel, and on 30.04.2012 WBSEDCL enquired about the status of coal lifting from that block (paras 8–9).
As the block could not be operationalised, APNRL sourced coal under tapering linkage from Central Coalfields Ltd. and claims to have met the shortfall through e-auction and imports. Its requests for pass-through of the extra cost were refused with reference to Article 2.5 (paras 10–11).
On 25.08.2014 the Supreme Court in Manohar Lal Sharma cancelled coal block allotments, including Ganeshpur, followed by the 2014 Ordinance and the Coal Mines (Special Provision) Act, 2015; APNRL was unsuccessful in the later bid. APNRL claimed Change in Law relief, and approached CERC in Petition No. 305/MP/2015 (paras 12–14).
CERC allowed compensation for e-auction/imported coal but rejected the Change in Law claim. On cross appeals, APTEL on 04.09.2025 upheld the coal cost compensation and also held the cancellation and the 2015 Act to be Change in Law events, remanding for compensation from 25.08.2014 with carrying costs. WBSEDCL appealed (paras 15–16).
Issues Before the Supreme Court
- Whether the PPA/PSA identified the Ganeshpur Coal Block as the captive source, though it was not expressly named (paras 17, 19–23).
- Whether cancellation of the coal block and the Coal Mines (Special Provision) Act, 2015 are Change in Law events under Article 10, notwithstanding Article 2.5 (para 24).
- Whether APNRL could recover the cost of e-auction/imported coal bought before 25.08.2014 to meet the tapering linkage shortfall (para 25).
Court's Findings and Reasoning
Rival submissions (paras 17–18): WBSEDCL argued that the PPA/PSA did not stipulate the source of coal and that Article 2.5 indemnified it against any escalation, so neither the cancellation nor the 2015 Act could be a Change in Law event. APNRL supported APTEL's award on both counts.
Ganeshpur is the captive source (paras 19–21): The argument was rebutted by the concurrent findings of CERC and APTEL. Read with the Minutes of Meeting dated 03.01.2011 and the letter dated 30.04.2012, the captive coal block in Article 2.5 refers to the Ganeshpur Coal Block.
Use of surrounding circumstances (paras 22–23): Relying on Anglo American Metallurgical Coal v. MMTC, the Court held that the rule that written terms are determined from the document does not bar facts that link the terms to attending circumstances or give meaning to a term. WBSEDCL was a party to the correspondence and never disputed it, so it could not deny that Ganeshpur was the captive source.
Change in Law from 25.08.2014 (para 24): In Manohar Lal Sharma, the Court interpreted the CMN Act and the MMDR Act differently from the Government of India and cancelled the allotments. That change in interpretation, and the 2015 Act, fall within Articles 10.1.1(b) and 10.1.1(f), and materially affected APNRL's right to procure coal from the block. Article 2.5 indemnifies against coal price escalation where coal is procured from other sources, while Article 10 is triggered when a Change in Law materially affects the right to operate the block. APTEL rightly reversed CERC on this point.
No compensation before cancellation (para 25): APTEL overlooked that the Minutes of Meeting recorded the allotment of the block and APNRL's assurance that it would be operational when supply began. Holding Article 2.5 inapplicable because of delay by the lead miner or the go-no-go policy was a restrictive reading that would expose WBSEDCL to coal cost escalation from unforeseen events other than Change in Law. GMR Kamalanga was distinguishable, as that PPA had no clause like Article 2.5.
Final Outcome and Directions
- Appeals partly allowed (para 26).
- APTEL's order dated 04.09.2025 set aside to the limited extent it grants compensation for e-auction/imported coal to meet the shortfall in tapering linkage pending operationalisation of the Ganeshpur coal block (para 26).
- Compensation on account of Change in Law events from 25.08.2014, with carrying costs till actual payment, upheld (para 26).
- CERC directed to modify its consequential order dated 11.02.2026 in terms of the judgment within four weeks; no order as to costs (para 26).
- Pending applications disposed of (para 27).
Legal Principle Laid Down
Where a power purchase contract refers to a "captive source" without naming it, its identity may be established from the surrounding circumstances and correspondence between the parties. A judicial change in the interpretation of mining law that cancels the captive coal block, and the legislation that follows, are Change in Law events under clauses like Articles 10.1.1(b) and 10.1.1(f). An indemnity clause against coal cost escalation from alternative sources operates in a different field from the Change in Law clause; it bars pass-through of extra coal costs incurred before the Change in Law event, but does not bar Change in Law compensation after it (paras 22–25).
Precedents Relied Upon
- Manohar Lal Sharma v. Principal Secretary, (2014) 9 SCC 516 – Referred to – cancellation of coal block allotments treated as a change in interpretation of law. Discussed at paras 12, 24.
- Anglo American Metallurgical Coal Pty. Limited v. MMTC Limited, (2021) 3 SCC 308 – Relied upon – use of surrounding facts to interpret a written contract under Sections 92, 94 and 95 of the Evidence Act. Discussed at para 22.
- GMR Kamalanga Energy Ltd. v. CERC, 2018 SCC OnLine Aptel 151 – Distinguished – that PPA had no indemnity clause like Article 2.5. Discussed at para 25.
Important Paragraphs of the Judgment
Verbatim extracts from the judgment. For the full text, refer to the judgment PDF below.
Para 21: "When Article 2.5 of PPA/PSA is read in light of these correspondences between the parties, there is no escape from the irresistible conclusion that the ‘captive coal block’ refers to the Ganeshpur Coal Block at Jharkhand."
Para 22: "Mr. Sibal’s argument that a written contract between parties cannot be qualified with reference to any prior or subsequent statements/conduct is unfounded."
Para 23: "In these circumstances, it does not lie in the mouth of WBSEDCL to contend that the PPA/PSA did not prescribe Ganeshpur Coal Block as the captive coal source for generation and supply of electricity."
Para 24: "This change in interpretation of the CMN Act, 1957 and the MMDR Act, 1957 by this Court resulting in cancellation of the coal blocks and subsequent promulgation of the Coal Mines (Special Provision) Act, 2015 falls within Articles 10.1.1(b) and 10.1.1(f) of the PPA/PSA."
Para 24: "WBSEDCL cannot claim immunity under Article 2.5 of the PPA/PSA. We say so as Article 2.5 and Article 10 operate in different fields."
Para 25: "Such restrictive interpretation of Article 2.5, in our considered opinion, is untenable, as it would expose WBSEDCL to the vagaries of coal cost escalation due to unforeseen events, save and except a Change in Law event under Article 10 of the PPA/PSA."
Practical Impact of the Ruling
- For generators: Loss of a captive coal block through the 2014 cancellations and the 2015 Act can be claimed as Change in Law, with carrying costs, from 25.08.2014 (para 24).
- For distribution companies: An indemnity clause against coal cost escalation is enforceable for the period before a Change in Law event, even where the captive block was delayed for reasons outside the generator's control (para 25).
- For contract drafting: An unnamed contractual term may be identified from minutes of negotiation and later correspondence, so parties should record the fuel source clearly (paras 22–23).
- For regulators: CERC must rework consequential orders to exclude pre-cancellation e-auction or import costs where an Article 2.5 type clause exists (para 26).
FAQs on Coal Block Cancellation and Change in Law
1. What did the Supreme Court decide in WBSEDCL v. Adhunik Power?
It upheld Change in Law compensation from 25.08.2014 with carrying costs but set aside APTEL's award of extra cost for e-auction or imported coal bought to meet the tapering linkage shortfall before the cancellation (para 26).
2. Is cancellation of a coal block by a court judgment a Change in Law?
Yes, on these facts. The change in interpretation of the CMN Act and the MMDR Act in Manohar Lal Sharma, resulting in cancellation, and the 2015 Act fall within Articles 10.1.1(b) and 10.1.1(f) (para 24).
3. Can a contract term be identified from documents outside the contract?
Yes. Facts that link the terms to attending circumstances, or give meaning to a term, may be considered; here the minutes and the letter of 30.04.2012 identified the captive source (paras 22–23).
4. Why was the pre-cancellation coal cost claim rejected?
Article 2.5 indemnified WBSEDCL against cost escalation when coal came from sources other than the captive source, and APNRL had assured that the block would be operational when supply began (para 25).
5. Does Article 2.5 bar Change in Law compensation?
No. Article 2.5 and Article 10 operate in different fields, so WBSEDCL cannot claim immunity under Article 2.5 from Change in Law compensation (para 24).
Keywords: 2026 INSC 202, WBSEDCL v. Adhunik Power, Change in Law, coal block cancellation, Manohar Lal Sharma, Coal Mines (Special Provision) Act 2015, Ganeshpur coal block, Article 2.5 PPA, tapering linkage, e-auction coal, carrying cost, APTEL, CERC, Anglo American Metallurgical Coal, contract interpretation, Justice Joymalya Bagchi, Supreme Court reportable judgment