Quick Answer: A writ court should not overturn an award of contract on the basis of a minuscule difference in evaluated scores when there is no arbitrariness or illegality in the owner's decision. The Supreme Court set aside a Gujarat High Court judgment that had quashed the Letter of Award and contract given to STEAG Energy Services for operation and maintenance of GPPC's gas-based power plant over a score difference of 0.00205301, holding that the final choice belongs to the owner and not the court.
In M/s. STEAG Energy Services (India) Pvt. Ltd. v. GSPC Pipavav Power Company Ltd. (GPPC) & Ors. (2026 INSC 295), the Supreme Court held that the High Court exceeded the principle of judicial restraint in contractual matters by itself awarding the contract to the rival bidder after a re-evaluation produced a tie in technical scores and a marginal difference in total scores, although the High Court had found no arbitrariness or illegality in the actions of the owner or its consultant (paras 17–18, 26–27). A Bench of Justice Pamidighantam Sri Narasimha and Justice Alok Aradhe upheld the Letter of Award dated 09.06.2025 and the contract dated 01.07.2025 in favour of STEAG, while rejecting its claim to additional marks for sea water system experience (paras 28–30).
Status: Gujarat High Court judgment in Special Civil Application No. 7289 of 2025 set aside and that appeal allowed; appeal arising out of Special Civil Application No. 12328 of 2025 dismissed; LOA and contract in favour of the appellant upheld; no costs (paras 28–31).
Headnote: Judicial Review of Tender Award on Marginal Score Difference
Constitution of India – Articles 14 and 226 – Judicial review of tenders and contracts – Quality and Cost Based System (QCBS) evaluation – Re-evaluation of technical marks by consultant – Tie in technical scores – Minuscule difference in total score – Owner's right to accept or reject bids – Fair play in the joints – Principle of judicial restraint – Letter of Award and executed contract.
Held: (i) Interference with a tender decision is permissible only where the decision-making process is mala fide, intended to favour someone, or so arbitrary, irrational or perverse that no responsible authority could have reached it; mere disagreement is no ground (paras 19–20).
(ii) Judicial review of contractual matters rests on two principles: restraint, and freedom of contract permitting free play in the joints (para 21).
(iii) The judicial solution to problems arising from fierce competition between bidders is not found in mathematical precision or rigid formulae; courts must balance justice with flexibility and keep in view the purpose of the tendering process (para 22).
(iv) Courts in judicial review cannot ignore the needs of the owner, including the speed at which it wants the appropriate contractor identified (para 24).
(v) Under the tender clause that the bidder with the highest total score "shall be considered", the entity to consider is the owner and not the court; constitutional courts should not exercise ex-ante jurisdiction to pre-empt executive actions (paras 25–26).
(vi) Counsel for a public body agreeing to a re-evaluation is not a ground for an intense inquiry; the burden is on the court to interfere only on settled principles (para 27).
(paras 19–30)
Case Details: STEAG Energy Services v. GSPC Pipavav Power Company (2026 INSC 295)
Final Outcome: Appeal arising out of Special Civil Application No. 7289 of 2025 allowed and the High Court's judgment set aside; LOA dated 09.06.2025 and contract dated 01.07.2025 in favour of the appellant upheld; appeal arising out of Special Civil Application No. 12328 of 2025 dismissed; no order as to costs.
Case: M/s. STEAG Energy Services (India) Pvt. Ltd. v. GSPC Pipavav Power Company Ltd. (GPPC) & Ors.
Neutral Citation: 2026 INSC 295
Case No.: Civil Appeal Nos. ___ of 2026 (arising out of SLP (C) Nos. 30209–30210 of 2025)
Court: Supreme Court of India (Civil Appellate Jurisdiction) – Reportable
Date of Decision: 25 March 2026
Bench: Justice Pamidighantam Sri Narasimha and Justice Alok Aradhe (authoring Judge not indicated in the judgment)
Relevant Acts & Sections: Constitution of India – Articles 14 and 226; Tender document of GPPC – Clauses 20.1, 20.2, 20.4, 20.5, 22.1 and 23.1
Impugned Order: Judgment and order of the High Court of Gujarat at Ahmedabad in Special Civil Application No. 7289 of 2025 and Special Civil Application No. 12328 of 2025 (para 2)
Counsel: Mr. D.V.S. Somayajulu, Senior Advocate, for the appellant; Ms. Meenakshi Arora, Senior Advocate, supporting the High Court's decision; Mr. Aspi M. Kapadia for GPPC (paras 19, 22, 27)
Source: Supreme Court of India (official website)
Key Holdings of the Supreme Court
- There was no justification to interfere with the LOA dated 09.06.2025 and the contract executed on 01.07.2025 (para 27).
- Given the marginal difference between the two bidders after re-evaluation, the High Court should have refrained from interfering (para 27).
- The High Court itself found no arbitrariness or illegality in the actions of GPPC or its consultant (para 18).
- Courts should not use a magnifying glass while scanning tenders and make every small mistake appear like a big blunder (para 23).
- Where the tender says the highest scorer "shall be considered", it is the owner, with the right to accept or reject any bid under Clause 23.1, that must consider (para 25).
- By substituting its own choice of contractor, the High Court exceeded the principle of judicial restraint in contractual matters (para 26).
- The High Court's finding rejecting the appellant's claim to 5 additional marks for sea water system experience was correct (para 28).
Brief Facts of the Case
GSPC Pipavav Power Company Ltd. (GPPC), which runs a 702.86 MW gas-based combined cycle power plant, floated a tender in January 2025 for its operation and maintenance for an initial period of five years. Bids were evaluated on a Quality and Cost Based System, with 70% weightage to technical score and 30% to price (paras 3–5).
Three of four bidders qualified. In the technical evaluation the appellant scored 95 and the writ petitioner, O&M Solutions Pvt. Ltd., scored 93, the difference arising from the appellant's 10 out of 10 marks for experience of planning and supervising major overhaul, HGPI and CI of a gas turbine. After the price evaluation by the consultant, Fichtner, the appellant was declared successful (para 7).
GPPC's Board resolved on 05.05.2025 to award the contract to the appellant, the LOA was issued on 09.06.2025, the appellant mobilised and took over the plant, and a formal contract was executed on 01.07.2025 (paras 8–9, 11).
The writ petitioner, which had not attended the pre-bid meeting or raised pre-bid queries, challenged the evaluation and then the LOA before the High Court. On the High Court's direction, Fichtner re-evaluated the technical bids and, by report dated 14.08.2025, reduced the appellant's marks on the experience item from 10 to 8, as one HGPI fell outside the evaluation period. Both bidders then had a technical score of 93 (paras 6, 12–15).
Comparing the prices of Rs. 19,65,55,668 and Rs. 19,65,69,120, the High Court found the writ petitioner's total score of 95.09989831 marginally higher than the appellant's 95.0978453, quashed the LOA and contract, and directed GPPC to award the contract to the writ petitioner (paras 16–18).
Issues Before the Supreme Court
- Whether the High Court, in judicial review, could quash an awarded and executed contract and direct award to the rival bidder on the basis of a minuscule difference in total score (paras 17–19, 27).
- Whether the High Court could rely on the tender clause on the highest total score to make the choice that belonged to the owner (paras 23, 25–26).
- Whether the appellant was entitled to additional marks for sea water system experience (para 28).
Court's Findings and Reasoning
Appellant's case (para 19): Senior Counsel relied on Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corpn. Ltd. to argue that the High Court seriously erred in interfering with the owner's decision when the difference between the bidders was marginal.
Settled limits of judicial review (paras 19–21): Following Afcons and Montecarlo Ltd. v. NTPC Ltd., the Court held that a tender decision may be interfered with only for mala fides, intent to favour someone, or arbitrariness, irrationality or perversity; technical evaluation or comparison by the court is impermissible, and the owner must be allowed free play in the joints.
Narrow price band no reason for rigid formulae (para 22): Senior Counsel supporting the High Court argued that a tender with maximum and minimum price benchmarks will inevitably produce marginal price differences. The Court accepted that this is true in highly competitive bidding, but held that the solution does not lie in mathematical precision; courts must exercise a nuanced discretion and not lose sight of the purpose of the tender.
Applying the contractual condition (para 23): To the argument that the High Court merely applied the tender condition, the Court referred to Tata Motors Ltd. v. BEST, which cautions courts against using a magnifying glass while scanning tenders.
Needs of the owner ignored (para 24): The parties and the Court lost sight of GPPC's requirements. The tender was floated in January 2025 and the LOA issued on 09.06.2025, more than a year earlier, and the Court asked who would account for the delay in executing the contract.
Choice belongs to the owner (paras 25–26): The clause that the highest scorer "shall be considered" leaves the consideration to the owner, which under Clause 23.1 may accept or reject any bid. Constitutional courts should not exercise ex-ante jurisdiction to pre-empt executive actions, and on this count the High Court exceeded judicial restraint.
Re-evaluation by consent no ground (para 27): GPPC's counsel agreeing to a re-evaluation could not be an additional ground for an intense inquiry. Cooperation by Government counsel is good practice at the Bar, but the burden of deciding whether to interfere rests on the court and must follow settled principles.
Sea water system marks (para 28): The appellant's claim to 5 additional marks under item 4 of the technical criteria was rejected, as the High Court's findings rested on correct facts and a reasonable interpretation of the tender document.
Final Outcome and Directions
- The appeal arising out of Special Civil Application No. 12328 of 2025, on the claim to additional sea water system marks, is dismissed (para 28).
- The LOA dated 09.06.2025 and the contract dated 01.07.2025 in favour of the appellant are upheld, and GPPC may have the contract performed without hindrance (para 29).
- The appeal arising out of Special Civil Application No. 7289 of 2025 is allowed and the High Court's judgment set aside (para 30).
- No order as to costs (para 31).
Legal Principle Laid Down
In judicial review of tenders, a writ court must exercise restraint and allow the owner free play in the joints. Where the owner's decision is free from mala fides, arbitrariness and illegality, the court should not quash an awarded and executed contract, or itself choose the successful bidder, because a re-evaluation shows a minuscule difference in scores. A tender clause that the highest scorer shall be considered for award leaves that consideration to the owner, not the court, and constitutional courts should not pre-empt executive choices in contractual matters (paras 21–22, 25–27).
Precedents Relied Upon
- Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corpn. Ltd., (2016) 16 SCC 818 – Relied upon – interference only for mala fides, favouritism, arbitrariness or perversity; quoting Central Coalfields Ltd. v. SLL-SML (Joint Venture Consortium). Discussed at para 19.
- Montecarlo Ltd. v. NTPC Ltd., (2016) 15 SCC 272 – Relied upon – restraint in technical tenders and free play in the joints. Discussed at paras 20–21.
- Tata Motors Ltd. v. Brihan Mumbai Electric Supply & Transport Undertaking (BEST), (2023) 19 SCC 1 – Relied upon – courts should not use a magnifying glass while scanning tenders. Discussed at para 23.
Important Paragraphs of the Judgment
Verbatim extracts from the judgment. For the full text, refer to the judgment PDF below.
Para 21: "The emphasis in the above referred decision is on two principles, the first being the principle of restraint in judicial review of contractual matters and the second being the freedom of contract permitting allowance of free play in the joints."
Para 22: "However, the judicial solution for such problems arising out of the fierce competition between competing bidders is not to be found in the mathematical precision or application of rigid formulae."
Para 24: "It is rather strange that in the whole process of judicial Scrutiny the contesting contractors as well as the Court lost sight of the needs and requirements of the Owner."
Para 25: "It is important to note that the entity to consider is the ‘Owner’ and not the court."
Para 26: "While exercising judicial review of contractual matters, constitutional courts do not exercise, should not exercise ex-ante jurisdiction to pre-empt executive actions."
Para 27: "However, we believe that the burden is always on the court and the decision to interfere with the process must be based on settled principles that we have indicated hereinabove."
Practical Impact of the Ruling
- For public sector owners: The choice of contractor among closely scored bidders remains theirs; courts will not substitute their own selection absent arbitrariness or mala fides (paras 25–26).
- For successful bidders: An awarded and executed contract is not to be undone merely because a later re-evaluation produces a fractional difference in scores (paras 27, 29).
- For unsuccessful bidders: Writ challenges based on minuscule score gaps under QCBS evaluations face a high threshold (paras 19–22).
- For High Courts: Re-evaluation ordered with the owner's consent does not justify an intense inquiry, and the needs and timelines of the owner must be weighed (paras 24, 27).
- For bid evaluation: Claims to technical marks are decided on the tender document; the Court upheld the denial of extra marks where the High Court's reading was reasonable (para 28).
FAQs on Judicial Review of Tender Awards
1. What did the Supreme Court decide in STEAG Energy Services v. GSPC Pipavav Power Company?
It set aside the Gujarat High Court's judgment quashing the LOA and contract given to STEAG and upheld the award, while dismissing STEAG's separate appeal on additional marks (paras 28–30).
2. Why did the High Court award the contract to the rival bidder?
After re-evaluation produced a tie in technical scores, it found the rival's total score marginally higher, 95.09989831 against 95.0978453, and relied on the clause that the highest scorer shall be considered (paras 15–18).
3. Why was the High Court's approach rejected?
The High Court found no arbitrariness or illegality in GPPC's actions, and a minuscule difference in score did not justify interference; the choice under the tender belonged to the owner (paras 18, 25–27).
4. Does a tender clause on the highest score bind the court to pick that bidder?
No. The Court held that the entity to consider under such a clause is the owner, which also has the right under Clause 23.1 to accept or reject any bid (para 25).
5. Did the owner's agreement to a re-evaluation change the position?
No. Counsel's cooperation with the court could not be an additional ground for an intense inquiry; the court must still interfere only on settled principles (para 27).
Keywords: 2026 INSC 295, STEAG Energy Services v. GSPC Pipavav Power Company, judicial review of tender, QCBS evaluation, marginal score difference, Letter of Award, fair play in the joints, judicial restraint in contractual matters, Afcons Infrastructure, Montecarlo v. NTPC, Tata Motors v. BEST, Article 226, Justice P.S. Narasimha, Justice Alok Aradhe, Supreme Court reportable judgment