Quick Answer: A party that consented twice before the High Court to a sole arbitrator, filed counter claims and agreed to extend the mandate cannot later insist on the three-member tribunal in the contract; it has waived that right under Sections 4 and 16 of the Arbitration Act. A corporate debtor under IBC moratorium can still pursue its own arbitral claim. But the power to extend an arbitrator's mandate under Section 29A lies with the "court" under Section 2(1)(e), not the High Court acting under Section 11.
In South Bihar Power Distribution Company Ltd. v. India Power Corporation Ltd. (2026 INSC 1165), the Supreme Court held that the appellant, having consented to the appointment and continuation of a sole arbitrator and having participated and filed counter claims, had waived its right to object to the absence of a three-member tribunal (paras 22, 25–27), and that the IBC moratorium does not bar a corporate debtor from pursuing its own arbitral claim (paras 29–31). A Bench of Justice Ujjal Bhuyan and Justice Atul S. Chandurkar, however, held that the Patna High Court erred in treating itself, as the Section 11 court, as competent to extend the mandate under Section 29A, since that power vests in the "court" under Section 2(1)(e) (paras 34–43). As the District Court had already extended the mandate, the appeals were dismissed and the arbitrator was directed to pass the award within six weeks (paras 44–47).
Status: Patna High Court's judgment dated 15.09.2023 upheld on waiver and locus (questions 1 and 2) but set aside on its holding that it could extend time under Section 29A (question 3); appeals dismissed; arbitrator to render award within six weeks (paras 45–47).
Headnote: Waiver of Three-Member Tribunal and Section 29A Court
Arbitration and Conciliation Act, 1996 – Sections 2(1)(e), 4, 11, 16(2), 29A(4), 29A(5), 42 – Waiver of right to object to composition of arbitral tribunal – Consent to sole arbitrator despite three-member clause – Acquiescence – Counter claim before sole arbitrator – Insolvency and Bankruptcy Code, 2016 – Section 14 moratorium – Corporate debtor pursuing arbitral claim – Section 28(1)(h) – Which court can extend arbitrator's mandate.
Held: (i) The High Court's orders dated 04.04.2018 and 10.03.2021 appointing sole arbitrators with the parties' consent were never challenged and have attained finality (para 22).
(ii) By consenting, participating, agreeing to extend the mandate and filing counter claims before the sole arbitrator, the appellant waived its right to object to the composition of the tribunal under Sections 4 and 16 and acquiesced in the proceedings; it could not raise the objection at the stage of a Section 29A extension (paras 23–27).
(iii) The Section 14 IBC moratorium bars recovery action against a corporate debtor but does not impair a claim by the corporate debtor, such as an arbitral claim; here the resolution professional's authorisation was approved by the committee of creditors under Section 28(1)(h) (paras 29–31).
(iv) The Supreme Court or the High Court acting under Section 11 is not the "court" defined in Section 2(1)(e); Section 11 jurisdiction is exhausted once the tribunal is constituted (paras 34, 37–40).
(v) The power to extend the mandate under Section 29A(4), and the consequential power of substitution under Section 29A(6), vests in the principal civil court of original jurisdiction or a High Court with ordinary original civil jurisdiction (paras 38–40, 43).
(vi) Since the Principal District Judge-cum-Commercial Court, Patna had already extended the mandate on 23.03.2026, setting aside the High Court's view on Section 29A did not alter the outcome (para 44).
(paras 14–47)
Case Details: South Bihar Power Distribution Co. v. India Power Corporation (2026 INSC 1165)
Final Outcome: Appeals dismissed; High Court upheld on waiver and locus of the corporate debtor, but its holding that it could extend time under Section 29A set aside; stay on the award lifted; arbitrator to conclude proceedings and pass the award within six weeks.
Case: South Bihar Power Distribution Company Ltd. v. India Power Corporation Ltd. & Anr.
Neutral Citation: 2026 INSC 1165
Case No.: Civil Appeal No. 9313 of 2026 (arising out of SLP (Civil) No. 27403 of 2023) with Civil Appeal No. 9325 of 2026 (arising out of SLP (Civil) No. 24988 of 2026)
Court: Supreme Court of India (Civil Appellate Jurisdiction) – Reportable
Date of Decision: 28 October 2026
Bench: Justice Ujjal Bhuyan (author) and Justice Atul S. Chandurkar
Relevant Acts & Sections: Arbitration and Conciliation Act, 1996 – Sections 2(1)(e), 4, 11, 13, 16, 29A, 42; Insolvency and Bankruptcy Code, 2016 – Sections 9, 14, 28(1)(h); Electricity Act, 2003 (background)
Impugned Order: Patna High Court – common judgment dated 15.09.2023 in Request Case No. 78 of 2022 and Request Case No. 36 of 2021 (para 2)
Counsel: Mr. Sundaram, Senior Advocate, for the appellant; Mr. Raju Ramachandran, Senior Advocate, for the appellant in the connected appeal; Mr. Atmaram Nadkarni, Senior Advocate, for Respondent No. 2 (paras 10–12)
Source: Supreme Court of India (official website)
Key Holdings of the Supreme Court
- Consent orders appointing a sole arbitrator that were never challenged attain finality and bind the parties (para 22).
- Participating, consenting to extension and filing counter claims before a sole arbitrator amounts to waiver under Section 4 and acquiescence; the three-member clause cannot be invoked belatedly (paras 23–27).
- The IBC moratorium does not stop a corporate debtor from pursuing its own arbitral claim (para 29).
- A High Court or the Supreme Court acting under Section 11 is not the "court" under Section 2(1)(e) (para 34).
- Section 29A(4) power to extend the mandate vests only in the court defined in Section 2(1)(e) (paras 38–40, 43).
- The arbitral proceedings must now conclude with an award within six weeks (para 46).
Brief Facts of the Case
The appellant, a distribution licensee in Bihar, entered into a Distribution Franchisee Agreement dated 31.12.2013 with India Power Corporation Ltd. (as confirming party) and its special purpose vehicle, India Power Corporation (Bodhgaya) Ltd. Clause 17.2.5 provided for arbitration by a panel of three arbitrators (paras 5–5.2, 14.1).
Disputes arose, and on a Section 11 request the Patna High Court, with the parties' consent, appointed a retired High Court Judge as sole arbitrator on 04.04.2018. The appellant later filed a counter claim and a supplementary counter claim (paras 5.3–5.4).
The NCLT admitted insolvency proceedings against the SPV (Respondent No. 2) on 08.11.2019; a resolution plan was later approved, and the SPV was renamed Vikriti Power Limited (paras 5.5, 5.9–5.10).
When the first arbitrator could not continue, the High Court, again with consent, appointed former Chief Justice of India Mr. Justice Dipak Misra as arbitrator on 10.03.2021. The parties recorded no objection to the sole arbitrator, and the mandate was extended by six months by consent (paras 5.6–5.7).
When that period was about to expire, the respondents sought a further extension in the High Court (Request Case No. 36 of 2021). The appellant opposed it and filed Request Case No. 78 of 2022 seeking a three-member tribunal. On 15.09.2023 the High Court extended the mandate by four months and rejected the appellant's request (paras 5.8, 5.11).
During the appeal, the Supreme Court allowed the arbitration to continue without declaring an award, and the District Court, Patna extended the mandate by six months on 23.03.2026 under Section 29A(5) (paras 6–9).
Issues Before the Supreme Court
- Whether the appellant had consented to, or acquiesced in, a sole arbitrator so as to waive the three-member tribunal clause (para 21).
- Whether Respondent No. 2, an SPV under the IBC moratorium, could pursue the arbitration (para 28).
- Whether the High Court exercising Section 11 power could extend the mandate under Section 29A, or only the "court" under Section 2(1)(e) (para 32).
Court's Findings and Reasoning
Appellant's case (paras 10–11): Senior Counsel argued that the agreement required a three-member tribunal, that Respondent No. 1 was only a proforma party whose consent was immaterial, that Respondent No. 2 had ceased to exist, and that the High Court had foisted a sole arbitrator on the appellant.
Respondent's case (para 12): Senior Counsel for Respondent No. 2 argued that substantial progress had been made and that aborting the arbitration would cause serious prejudice.
Consent and finality (paras 21–22): The appellant had consented before the High Court twice and before the arbitrator, and had never challenged the appointment orders of 04.04.2018 and 10.03.2021, which therefore attained finality.
Waiver and acquiescence (paras 23–27): Under Sections 4 and 16(2), a party that proceeds with arbitration without timely objection is deemed to have waived it. Relying on Union of India v. Pam Development, the Court held that participation, consent to extension and counter claims amounted to clear acquiescence, and the objection could not be raised at the Section 29A stage.
IBC moratorium and locus (paras 28–31): Section 14 IBC prohibits recovery action against the corporate debtor but not its own claims; an arbitral claim, if successful, enhances the debtor's value. The resolution professional had authorised the arbitration with CoC approval under Section 28(1)(h).
Which court under Section 29A (paras 32–43): Section 2(1)(e) exhaustively defines "court" as the principal civil court of original jurisdiction or a High Court with ordinary original civil jurisdiction. Relying on Associated Contractors, BSC & C and C JV, Jagdeep Chowgule and C. Velusamy, the Court held that Section 11 jurisdiction ends once the tribunal is constituted, and the Section 29A power vests in the Section 2(1)(e) court, not the Section 11 High Court.
Effect on outcome (para 44): Since the District Court had already extended the mandate on 23.03.2026, setting aside the High Court's view on question 3 did not materially affect the outcome.
Final Outcome and Directions
- High Court's judgment dated 15.09.2023 upheld on questions 1 (waiver) and 2 (locus of the corporate debtor) (para 45).
- High Court's holding that it could extend time under Section 29A as the Section 11 court set aside (paras 43, 45).
- The embargo of 12.02.2024 on declaring the award lifted (para 46).
- The arbitrator shall conclude the proceedings and pass the award within six weeks (para 46).
- Civil appeals dismissed; no costs (paras 47–48).
Legal Principle Laid Down
A party that knowingly consents to and participates in arbitration before a sole arbitrator, including by filing counter claims and agreeing to extensions, waives its right under Sections 4 and 16 of the Arbitration and Conciliation Act, 1996 to insist on a differently constituted tribunal. The IBC moratorium does not prevent a corporate debtor from pursuing its own arbitral claims. The power to extend an arbitrator's mandate under Section 29A belongs to the "court" defined in Section 2(1)(e), not to the High Court or the Supreme Court exercising Section 11 jurisdiction.
Precedents Relied Upon
- Union of India v. Pam Development Pvt. Ltd., (2014) 11 SCC 366 – Relied upon – participation and counter claim amount to waiver under Sections 4 and 16. Discussed at para 26.
- State of West Bengal v. Associated Contractors, (2015) 1 SCC 32 (three-Judge Bench) – Relied upon – Section 2(1)(e) is exhaustive; Section 11 authority is not "court". Discussed at para 37.
- Chief Engineer (NH) PWD (Roads) v. M/s BSC & C and C JV (SLP (C) No. 10544 of 2024, decided 13.05.2024) – Relied upon – Section 29A(4) power vests in the Section 2(1)(e) court. Discussed at para 38.
- Jagdeep Chowgule v. Sheela Chowgule, (2026) 5 SCC 667 – Relied upon – Section 11 jurisdiction exhausted after appointment. Discussed at para 39.
- C. Velusamy v. K. Indhera, (2026) 5 SCC 340 – Relied upon – contours of Section 29A and identity of the court. Discussed at paras 19, 40, 42.
- Rohan Builders (India) (P) Ltd. v. Berger Paints (India) Ltd., (2025) 10 SCC 802 – Referred – extension application maintainable after expiry. Discussed at paras 18, 41.
Important Paragraphs of the Judgment
Verbatim extracts from the judgment. For the full text, refer to the judgment PDF below.
Para 22: "Consequently, those orders have attained finality and are binding on the parties."
Para 25: "... by its conduct, the appellant had clearly waived its right to object to the composition of the arbitral tribunal within the time limit provided by the statute."
Para 29: "The moratorium provided for in Section 14 of the IBC is intended to prohibit debt recovery action against the corporate debtor so as not to adversely impact the insolvency process; however, it would not impair any claim by the corporate debtor, such as, an arbitral claim, which if successful, would only bolster the financial health thereby enhancing the value of the corporate debtor."
Para 34: "Therefore, the Supreme Court or the High Court referred to in Section 11 cannot be deemed to be the ‘court’ as defined in Section 2(1)(e)."
Para 43: "... the Chief Justice of the High Court or his designate empowered under Section 11 of the 1996 Act can grant extension of time under Section 29A(4) is clearly unsustainable in law."
Para 46: "The learned arbitrator shall now conclude the arbitral proceedings by passing the award within a period of 6(six) weeks from today."
Practical Impact of the Ruling
- For parties to arbitration: Consenting to a sole arbitrator and participating fully waives a multi-member tribunal clause; objections must be raised promptly (paras 23–27).
- For extension applications: Applications under Section 29A(5) must go to the Section 2(1)(e) court, such as the commercial court, not the High Court that appointed the arbitrator under Section 11 (paras 38–43).
- For resolution professionals and CoCs: A corporate debtor's arbitral claims can continue during the moratorium with proper authorisation under Section 28(1)(h) (paras 29–30).
- For distribution licensees and franchisees: Tripartite franchisee disputes may proceed with the SPV as claimant even after insolvency (paras 28–31).
- For arbitrators: Long-pending references may be given a tight deadline once the Supreme Court lifts an interim embargo (para 46).
FAQs on Waiver of Tribunal Composition and Section 29A
1. What did the Supreme Court hold in South Bihar Power Distribution Co. v. India Power Corporation?
It held that the appellant waived the three-member tribunal clause by its consent and conduct, that the IBC moratorium did not bar the corporate debtor's arbitral claim, and that only the Section 2(1)(e) court can extend time under Section 29A (paras 27, 31, 43).
2. Can a party object to a sole arbitrator after consenting and filing a counter claim?
No. Such conduct amounts to waiver under Sections 4 and 16 and to acquiescence (paras 25–27).
3. Does the IBC moratorium stop a corporate debtor's own arbitration?
No. Section 14 bars recovery against the corporate debtor, not claims by it (para 29).
4. Which court can extend an arbitrator's mandate under Section 29A?
The principal civil court of original jurisdiction, or a High Court with ordinary original civil jurisdiction, under Section 2(1)(e); not the High Court acting under Section 11 (paras 34, 38–43).
5. What happens to the arbitration now?
The interim embargo was lifted and the arbitrator must pass the award within six weeks (para 46).
Keywords: 2026 INSC 1165, South Bihar Power Distribution Company v. India Power Corporation, Section 29A Arbitration Act, extension of arbitrator mandate, Section 2(1)(e) court, Section 11, waiver Section 4, Section 16(2), sole arbitrator three-member clause, IBC moratorium arbitral claim, Section 14 IBC, Justice Ujjal Bhuyan, Supreme Court reportable judgment, arbitration law