Quick Answer: The cess under the Building and Other Construction Workers' Welfare Cess Act, 1996 could not be levied or collected until a Welfare Board was constituted in the State concerned. Contractors who bid before that could not have priced the cess into their bids, so arbitral awards treating the later levy as "subsequent legislation" under NHAI's contracts were plausible and were upheld; NHAI's five appeals were dismissed and Prakash Atlanta (JV)'s appeal was allowed.
In Prakash Atlanta (JV) v. National Highways Authority of India (2026 INSC 76), the Supreme Court held that the BOCW Act and the Cess Act, though in force from 1996 and 1995, remained dormant until Welfare Boards were constituted, and that the constitution of Welfare Boards is the sine qua non for levy and collection of the cess (paras 35–37, 50, 59). As none of the contractors' bids was submitted when a Welfare Board existed, the arbitral tribunals' reading of Clauses 14.3 and 70.8 ("Subsequent Legislation") was a plausible view not open to interference under Sections 34 and 37 of the Arbitration Act (paras 51–52, 59). A Bench of Justice Sanjay Kumar and Justice Alok Aradhe dismissed NHAI's five appeals and allowed Prakash Atlanta (JV)'s appeal (para 60).
Status: Civil Appeal Nos. 5301, 5302, 5304, 5412 and 5416 of 2025 filed by NHAI dismissed; Civil Appeal No. 4513 of 2025 filed by Prakash Atlanta (JV) allowed and the executing Court's and appellate Court's orders set aside; NHAI to release the cess amount adjusted from the award dated 26.06.2004 with interest as per the award (para 60).
Headnote: BOCW Cess and the Subsequent Legislation Clause
Arbitration and Conciliation Act, 1996 – Sections 28(1)(a), 34 and 37 – Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 – Sections 2(1)(i), 18 – Building and Other Construction Workers' Welfare Cess Act, 1996 – Section 3 – Cess Rules, 1998 – Rules 4 and 5 – NHAI contracts – Clause 14.3 and Clause 70.8 (Subsequent Legislation) – Levy of cess before constitution of Welfare Boards – Plausible view of arbitral tribunal – Public policy – Patent illegality.
Held: (i) The BOCW Act and the Cess Act came into force on the notified dates but could not be given effect till Welfare Boards were constituted under Section 18 of the BOCW Act; they remained dormant owing to the failure of the appropriate Governments (paras 35, 37, 59(ii)).
(ii) The Cess Act is complementary to the BOCW Act and was enacted to augment the resources of the Welfare Boards; without such Boards, levy and collection of cess did not arise, and deduction at source under Rule 4(3) could not be deposited as Rule 5 requires (paras 35–37, 59(iii)).
(iii) Following A. Prabhakara Reddy, constitution of Welfare Boards is a condition precedent for the levy and collection of the cess, though registration of workers or provision of welfare measures is not (paras 50, 53, 59(iv)).
(iv) Contractors could not have factored the cess into bid prices before a mechanism for its collection was in place, as that would have led to unjust and unlawful enrichment; mere mention of the two Acts in Clause 34.2 of NHAI's contracts had no significance without that machinery (paras 50–51, 59(v)).
(v) The observation in para 18 of Dewan Chand Builders that the Cess Act became operative in Delhi from January 2002 was not a stray observation but an affirmation of the Delhi High Court's finding (paras 53, 59(i)).
(vi) Construction of a contract is for the arbitral tribunal; the tribunals' reading of Clauses 14.3 and 70.8 was plausible, not perverse or patently illegal, not opposed to the public policy of India and not in breach of Section 28(1)(a) (paras 34, 52, 59(vi)–(vii)).
(paras 35–60)
Case Details: Prakash Atlanta (JV) v. NHAI (2026 INSC 76)
Final Outcome: NHAI's five appeals dismissed; Prakash Atlanta (JV)'s appeal allowed; NHAI to release the adjusted cess amount with interest as per the award dated 26.06.2004; IA Nos. 77056 of 2013 and 2 of 2013 allowed; intervention application of M/s. Centrodorstroy rejected (paras 58, 60).
Case: Prakash Atlanta (JV) v. National Highways Authority of India, with five connected appeals filed by NHAI
Neutral Citation: 2026 INSC 76
Case No.: Civil Appeal No. 4513 of 2025 with Civil Appeal Nos. 5416, 5302, 5301, 5304 and 5412 of 2025
Court: Supreme Court of India (Civil Appellate Jurisdiction) – Reportable
Date of Decision: 20 January 2026
Bench: Justice Sanjay Kumar (author) and Justice Alok Aradhe
Relevant Acts & Sections: Arbitration and Conciliation Act, 1996 – Sections 28(1)(a), 34, 34(2A) and 37; Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 – Sections 1, 2(1)(i), 18, 24, 62; Building and Other Construction Workers' Welfare Cess Act, 1996 – Section 3; Building and Other Construction Workers' Welfare Cess Rules, 1998 – Rules 4, 5 and 7
Impugned Orders: Delhi High Court – orders of the executing Court dated 09.11.2012 and of the Division Bench dated 12.02.2013 in EFA (OS) No. 4 of 2012 (Prakash Atlanta); and Division Bench orders dismissing NHAI's Section 37 appeals, dated 14.08.2013 (FAO (OS) No. 366 of 2013), 11.03.2014 (FAO (OS) No. 128 of 2014), 10.01.2017 (FAO (OS) (COMM) No. 11 of 2017), 23.03.2018 and 14.03.2019 (FAO (OS) (COMM) No. 20 of 2019) (paras 43–48)
Source: Supreme Court of India
Key Holdings of the Supreme Court
- The BOCW Act and the Cess Act remained dormant, in fact, until Welfare Boards were constituted; the failure lies at the door of the Central and State/UT Governments (paras 35–37, 59(ii)).
- Constitution of Welfare Boards is the sine qua non for levy and collection of cess under the two Acts (paras 50, 59(iv)).
- In none of the six cases did a Welfare Board exist when the contractors submitted their bids, so factoring the cess into bid prices did not arise (para 51).
- The arbitral tribunals' construction of the 28-day bid-related cut-off in Clauses 14.3 and 70.8 was plausible and cannot be substituted by the Court (para 52).
- NHAI's attempt to recover cess from Prakash Atlanta (JV) only in execution proceedings was an afterthought, and liability could not be imposed retrospectively after termination of its contract (para 54).
- The award on the foreign currency price adjustment claim (Claim 4) in the Hindustan Construction Co. Ltd. case and NHAI's note on other claims in the Gammon-Atlanta (JV) case were not interfered with (paras 55–57).
Brief Facts of the Case
The BOCW Act came into force on 01.03.1996 and the Cess Act on 03.11.1995. The Central Government fixed the cess at 1 per cent of the cost of construction by notification dated 26.09.1996. The Acts were not actually implemented until the Supreme Court monitored their implementation in the National Campaign Committee case (paras 2, 9, 14–17).
NHAI's contracts contained Clause 14.3, requiring duties, taxes and levies as of 28 days before the bid deadline to be included in the bid price, and Clause 70.8, providing for additional cost due to later changes in or introduction of law. In three contracts, Clause 34.2 listed the BOCW Act and the Cess Act among the labour laws to be complied with (paras 38–40).
The contractors' bids were submitted between 2000 and 2008, before the States concerned (Odisha, Jharkhand, Gujarat and Uttar Pradesh) put Welfare Boards and cess collection in place. Arbitral tribunals in the five NHAI cases held the later levy to be "subsequent legislation" and directed reimbursement of cess deducted; the Delhi High Court upheld the awards under Sections 34 and 37 (paras 44–48, 51).
Prakash Atlanta (JV)'s contract of 10.08.2001 had no Clause 14.3 or 70.8 and was terminated on 14.03.2008. Uttar Pradesh's Circular dated 17.02.2010 applied the cess to projects ongoing on 04.02.2009. In execution of the 2004 award in its favour, NHAI adjusted cess, which the Delhi High Court permitted on 09.11.2012 and affirmed on 12.02.2013 (paras 41–43).
Issues Before the Supreme Court
- Whether the BOCW Act and the Cess Act could be treated as "subsequent legislation" for NHAI's contracts, when they came into force in 1995–96 but Welfare Boards were constituted much later (paras 1, 17, 35).
- Whether the arbitral awards so holding were open to interference under Sections 34 and 37 of the Arbitration Act (paras 23, 34, 52).
- Whether Prakash Atlanta (JV), whose contract had no subsequent legislation clause, could be made liable for cess in execution proceedings (para 54).
Court's Findings and Reasoning
Scope of review (paras 23–34): Reviewing Associate Builders, Western Geco, ITD Cementation, Ssangyong, MMTC, OPG Power and other decisions, the Court noted that three awards fell to be tested under the pre-2015 law and two under amended Section 34 including patent illegality; either way, no merits-based evaluation or appeal over a plausible view on facts is permitted.
Cess Act dependent on Welfare Boards (paras 35–36): The Cess Act exists to augment the resources of Welfare Boards, so bringing it into force before the BOCW Act was "putting the cart before the horse", and it could not operate in a vacuum before the Boards existed. Cess collected without a Board would have gone into the consolidated fund, making its character as a fee rather than a tax debatable.
Deduction at source (para 37): Rule 4(3) deductions must be transferred to the Welfare Board under Rule 5, which was impossible without a Board. NHAI admittedly made no such deductions at the time and sought recoveries only later.
Liability and bid prices (paras 50–51): The employer, including the contractor, bears the cess under Section 3(2) of the Cess Act, but contractors could not have priced a levy that had no collection mechanism. On the facts, every bid preceded the relevant State's Board or cess notification.
Interpretation of the contract (para 52): NHAI's argument that Clause 70.8 covers only changes in existing law or new laws overlooked the 28-day timeframe tied to the bid deadline, on which the tribunals based their reading. Their view was not arbitrary, perverse or patently illegal.
Dewan Chand Builders (para 53): Its para 18 affirmed the Delhi High Court's finding, and A. Prabhakara Reddy settled that Welfare Boards were essential to give actual effect to the Acts.
Prakash Atlanta (JV) (para 54): NHAI never raised cess in the arbitration, the Section 34 and 37 proceedings or review, and raised it only in execution in September 2012. This was an afterthought, and the contractor could not be burdened retrospectively long after its contract ended.
Final Outcome and Directions
- Civil Appeal Nos. 5301, 5302, 5304, 5412 and 5416 of 2025 filed by NHAI dismissed (para 60).
- Civil Appeal No. 4513 of 2025 allowed; the orders holding Prakash Atlanta (JV) liable for cess set aside (para 60).
- NHAI to release the amount adjusted from the amounts payable under the award dated 26.06.2004, with interest as per that award (para 60).
- IA No. 84855 of 2015 for intervention by M/s. Centrodorstroy rejected along with its additional grounds (para 58).
- IA Nos. 77056 of 2013 and 2 of 2013 allowed; other pending applications disposed of (para 60).
Legal Principle Laid Down
Cess under the Building and Other Construction Workers' Welfare Cess Act, 1996 cannot be levied or collected before a Welfare Board is constituted under Section 18 of the BOCW Act, though registration of workers or provision of welfare measures is not a precondition. Where a contractor's bid preceded the constitution of the Board, an arbitral tribunal's view that the later levy is "subsequent legislation" under a bid-date-linked clause is a plausible construction of the contract that courts will not disturb under Sections 34 and 37 (paras 50–52, 59).
Precedents Relied Upon
- Dewan Chand Builders and Contractors v. Union of India, (2012) 1 SCC 101 – Relied upon – Cess Act operative in Delhi from January 2002; levy is a fee, not a tax. Discussed at paras 21, 53.
- A. Prabhakara Reddy and Company v. State of Madhya Pradesh, (2016) 1 SCC 600 – Relied upon – constitution of Welfare Board essential; registration of workers not a precondition. Discussed at paras 22, 50, 53.
- National Campaign Committee, C.L., Labour v. Union of India, (2009) 3 SCC 269 and (2018) 5 SCC 607 – Referred to – non-implementation of the two Acts. Discussed at paras 14–16.
- Gayatri Balasamy v. ISG Novasoft Technologies Limited, (2025) 7 SCC 1 – Relied upon – limited power to modify awards. Discussed at para 23.
- Associate Builders v. Delhi Development Authority, (2015) 3 SCC 49 – Relied upon – public policy test; arbitrator is master of facts. Discussed at paras 24, 26, 34.
- National Highways Authority of India v. ITD Cementation India Limited, (2015) 14 SCC 21 – Relied upon – construction of contract is for the arbitrator; subsequent legislation clause. Discussed at paras 27–28.
- OPG Power Generation Private Limited v. Enexio Power Cooling Solutions India Private Limited, (2025) 2 SCC 417 – Relied upon – restricted meaning of fundamental policy of Indian law. Discussed at para 33.
- UHL Power Company Limited v. State of Himachal Pradesh, (2022) 4 SCC 116 and Ssangyong Engineering and Construction Company Limited v. NHAI, (2019) 15 SCC 131 – Relied upon – plausible interpretation of contract not to be disturbed. Discussed at para 29.
Important Paragraphs of the Judgment
Verbatim extracts from the judgment. For the full text, refer to the judgment PDF below.
Para 35: "This was clearly a case of putting the cart before the horse!"
Para 36: "In the absence of such machinery, the question of levying and collecting cess cannot logically arise."
Para 37: "The failure to effectively implement the BOCW Act and the Cess Act has to be laid squarely at the door of the authorities, i.e., the Central Government and the Governments of the States/UTs concerned."
Para 50: "The answer is simple - the contractors could not have factored such cess component into their bid prices prior to a mechanism being put in place for its collection, as that would have led to unjust and unlawful enrichment on their part."
Para 52: "Once the view taken by the arbitral tribunal is found to be a plausible and possible one on facts and not an unreasonable one, it is not for the Courts, under Sections 34 or 37 of the Arbitration Act, or for this Court to sit in appeal or substitute its view for that of the arbitral tribunal."
Para 54: "Thus, it was clearly an afterthought on the part of NHAI."
Practical Impact of the Ruling
- For contractors: Where the bid preceded the constitution of the Welfare Board in the State, cess deducted later can be claimed under a bid-date-linked change-in-law clause (paras 51–52).
- For NHAI and public employers: A bare reference to the BOCW Act and the Cess Act in the labour-law clause does not shift the cess burden to the contractor when no collection machinery existed (para 59(v)).
- For award-holders: New set-offs raised for the first time in execution, after the award has attained finality, may be rejected as an afterthought (para 54).
- For courts: Plausible arbitral constructions of contract clauses are not to be substituted under Sections 34 or 37, or under Article 136 (paras 34, 52).
- For States: The levy depends on functioning Welfare Boards; collection without them risks altering the cess's character as a fee (paras 36, 59(iii)).
FAQs on BOCW Cess and Subsequent Legislation
1. What did the Supreme Court decide in Prakash Atlanta (JV) v. NHAI?
It dismissed NHAI's five appeals against arbitral awards directing reimbursement of BOCW cess, and allowed Prakash Atlanta (JV)'s appeal against recovery of cess in execution (para 60).
2. When can BOCW welfare cess be levied?
Only after a Welfare Board is constituted under Section 18 of the BOCW Act; registration of workers or provision of welfare measures is not required first (paras 50, 59(iv)).
3. Did the dates of commencement of the two Acts in 1995 and 1996 matter?
The Acts were in force from those dates but remained dormant until the machinery for levy, collection and deposit of cess was put in place (paras 35, 37, 59(ii)).
4. Why did the Court not interfere with the arbitral awards?
The tribunals' reading of Clauses 14.3 and 70.8 was a plausible view, not perverse, patently illegal or against public policy, and not in breach of Section 28(1)(a) (paras 52, 59(vi)–(vii)).
5. Why did Prakash Atlanta (JV) succeed without a subsequent legislation clause?
NHAI raised cess only in execution, long after the award and after the contract's termination; this was an afterthought, and the cess could not be imposed retrospectively (para 54).
Keywords: 2026 INSC 76, Prakash Atlanta (JV) v. NHAI, BOCW Act, Building and Other Construction Workers' Welfare Cess Act, welfare cess, Welfare Board, subsequent legislation clause, Clause 70.8, Clause 14.3, Section 34 Arbitration Act, Section 37 Arbitration Act, patent illegality, public policy, Dewan Chand Builders, A. Prabhakara Reddy, Justice Sanjay Kumar, Justice Alok Aradhe, Supreme Court judgment
Related on LegalTaxGuru
Download Judgment PDF – Prakash Atlanta (JV) v. NHAI
Source: Supreme Court of India (official website).