Quick Answer: A Railways tender bid cannot be rejected for not submitting the "original" bid security when the bid security was paid by e-payment and the digital receipt was uploaded. The Supreme Court called the rejection perverse, since producing an original of an online payment is an impossibility, set aside the Patna High Court's order and directed that the appellant's financial bid be opened.
In Hardev Construction Private Limited v. Union of India & Ors. (2026 INSC 1110), the Supreme Court held that rejecting a bid for non-submission of the original bid security, when the security had been paid through the e-payment gateway and the digital receipt uploaded, was a clear perversity, because a physical original of an e-payment is an impossibility (paras 7–10). A Bench of Justice J.B. Pardiwala and Justice K. Vinod Chandran (author) set aside the Patna High Court's order, held that rigid adherence to the letter of a tender document cannot be countenanced where compliance is impossible, and directed that, on fresh submission of the bid security, the appellant's financial bid be opened and considered with the others (paras 10–12).
Status: Patna High Court Division Bench's order affirming rejection of the bid set aside; appeal allowed with directions to accept fresh bid security and open the appellant's financial bid (paras 11–13).
Headnote: E-Payment Bid Security and Demand for Original
Constitution of India – Article 226 – Government contracts – Tender – Request for Proposal – Clause 2.20.6(ii) – Bid security paid by e-payment gateway – Requirement to physically submit original – Impossibility of compliance – Perverse application of tender terms – Judicial review – Deference to tendering authority – Exception for mala fide or perverse interpretation.
Held: (i) The requirement to physically deliver the original bid security makes sense for bank guarantees, demand drafts, FDRs and banker's cheques, since no lien can be exercised on them unless the originals reach the authority (paras 8, 10).
(ii) Where bid security is paid by e-payment, the money is already in the authority's account and under its full control, and nothing further needs to be produced once the digital receipt is uploaded (paras 8, 10).
(iii) Rejecting the bid only because an "original" of the e-payment was not produced is a clear perversity, as compliance is an impossibility (para 10).
(iv) Rigid adherence to the letter of a tender document cannot be countenanced when compliance is clearly impossible (para 10).
(v) Prakash Asphaltings, which counsels deference to the tendering authority's reading of its documents, itself carves out an exception for mala fide and perverse understanding or application of tender terms (para 9).
(vi) As the earlier deposit had been refunded, the appellant is to furnish bid security afresh, after which its financial bid is to be opened and considered with the other bids (para 12).
(paras 7–12)
Case Details: Hardev Construction v. Union of India (2026 INSC 1110)
Final Outcome: Appeal allowed; Patna High Court's order set aside; rejection of the appellant's bid quashed; bid security to be furnished afresh and the appellant's financial bid opened and considered.
Case: Hardev Construction Private Limited v. Union of India & Ors.
Neutral Citation: 2026 INSC 1110
Case No.: Civil Appeal No. ___ of 2026 (arising out of SLP (C) No. 25855 of 2026)
Court: Supreme Court of India (Civil Appellate Jurisdiction) – Non-Reportable
Date of Decision: 12 October 2026
Bench: Justice J.B. Pardiwala and Justice K. Vinod Chandran (author)
Relevant Acts & Sections: Constitution of India – judicial review of tender decisions; Request for Proposal – Clause 2.20.6 (bid security) and Clause 2.20.6(ii) (physical submission of original)
Impugned Order: Division Bench of the Patna High Court affirming rejection of the appellant's bid (para 2)
Counsel: Sri A.K. De for the appellant; Sri Kanakamedala Ravindra Kumar, learned ASG, for the Ministry of Railways; Ms. Nina R. Nariman for the 3rd respondent, the successful tenderer (para 3)
Source: Supreme Court of India (official website)
Key Holdings of the Supreme Court
- Bid security paid by e-payment, with the digital receipt uploaded, needs no "original" to be physically submitted (para 8).
- Rejecting a bid for not producing an original that cannot exist is a clear perversity (para 10).
- Rigid adherence to the letter of a tender document cannot be countenanced where compliance is impossible (para 10).
- Deference to the tendering authority's interpretation does not extend to perverse application of tender terms (para 9).
- The appellant must furnish bid security afresh, after which its financial bid is to be opened and considered (para 12).
Brief Facts of the Case
The appellant bid for an EPC contract for guide bunds, launching aprons and river protection works for the Bikramshila-Katareah New Line Rail Link Project, under a tender dated 06.01.2026 (para 2).
The appellant paid its bid security through the e-payment gateway of the authority, and scanned and uploaded the digital receipt with its bid (paras 4, 7).
The bid was rejected for non-submission of the original bid security under Clause 2.20.6(ii) of the RFP. The appellant's technical bid failed on that ground, so its financial bid was never opened (paras 2, 6).
A Division Bench of the Patna High Court affirmed the rejection, leading to this appeal (para 2).
Issues Before the Supreme Court
- Whether a bid can be rejected for not physically submitting the original bid security when the security was paid through e-payment and the receipt was uploaded (paras 4–5, 7–8).
- Whether deference to the tendering authority's reading of the tender documents protects such a rejection (paras 5, 9).
- What relief should follow, given that the deposit had been refunded (para 12).
Court's Findings and Reasoning
Rival submissions (paras 4–6): The appellant argued that its e-payment had already reached the respondents. The ASG relied on the express requirement in Clause 2.20.6(ii), and the 3rd respondent relied on Prakash Asphaltings for deference to the awarding authority. The ASG also pointed out that the appellant's financial bid was never opened.
Purpose of the clause (paras 7–8): Clause 2.20.6 allows bid security as a bank guarantee, demand draft, FDR, banker's cheque or e-payment. For the physical instruments, no lien can be exercised unless the original is handed over, which is why a scanned copy is uploaded first and the original delivered later. For e-payment, the money is already in the respondents' account.
Prakash Asphaltings distinguished (para 9): That case concerned a tenderer who quoted a paltry amount and tried to explain it as a per-day rate; the Court held the tender's words could not be ignored. It also carved out an exception for mala fide and perverse understanding or application of tender documents.
Clear perversity (para 10): Rejecting a bid whose e-payment was made and receipt uploaded, only because the original was not produced, was a clear perversity, since producing an original was an impossibility.
Relief (paras 11–12): The Court set aside the impugned order. As the deposit had been refunded, respondents 1 and 2 must facilitate e-payment within two weeks, failing which the appellant may submit the amount in another form within a further two weeks; its financial bid is then to be opened and the tender finalised under the other conditions.
Final Outcome and Directions
- Impugned order of the Patna High Court set aside (para 11).
- Respondent Nos. 1 and 2 to facilitate e-payment of the bid security within two weeks; if there is a technical difficulty, the appellant to submit the amount in any other form within a further two weeks (para 12).
- On submission of the bid security, the appellant's financial bid to be opened and considered along with the other bids, and the tender finalised in accordance with the other tender conditions (para 12).
- Appeal allowed with these directions; pending applications rejected (paras 13–14).
Legal Principle Laid Down
A tender condition requiring physical submission of the original bid security cannot be applied to a bid whose security was paid by e-payment and whose digital receipt was uploaded, because compliance is impossible and the money is already under the authority's control. Rejecting such a bid is a perverse application of the tender terms, which falls within the exception to the rule of deference to the tendering authority (paras 8–10).
Precedents Relied Upon
- Prakash Asphaltings and Toll Highways (India) Ltd. v. Mandeepa Enterprises and Others, (2026) 4 SCC 310 – Distinguished – deference to the authority's reading of tender documents, subject to an exception for mala fide and perverse understanding or application. Discussed at paras 5, 9.
Important Paragraphs of the Judgment
Verbatim extracts from the judgment. For the full text, refer to the judgment PDF below.
Para 8: "Insofar as the appellant is concerned, the money was deposited to the account of the respondents and there is nothing further required to be produced insofar as the e-payment made, especially when the digital payment receipt had been uploaded along with the bid document."
Para 9: "It is also pertinent that this Court in the aforesaid decision, while cautioning the Constitutional Court’s to defer to the understanding and appreciation of the tender documents, also carved out an exception insofar as mala fide and perverse understanding or appreciation of the documents, especially in the application of the terms of the tender document."
Para 10: "We are convinced that here, there is a clear perversity; insofar as an e-payment was made, as required by the tender document, the digital receipt of which was scanned and uploaded, rejected only since the original was not produced; which is an impossibility."
Para 10: "Rigid adherence to the letter of a document cannot be countenanced, especially when there is a clear impossibility in compliance of the same."
Para 10: "However, insofar as the e-payment is concerned, the money has already been transferred to the account of the respondents, and they have full control over it."
Para 12: "On the submission of the Bid Security, the appellant’s financial bid shall be opened to be considered along with the other bids and the tender finalized, in accordance with the other tender conditions stipulated."
Practical Impact of the Ruling
- For bidders: Bid security paid by e-payment, with the receipt uploaded, cannot be a ground for rejection for want of an "original" (paras 8, 10).
- For Railways and public authorities: Tender clauses written for physical instruments must be applied sensibly to e-payments; a perverse application invites judicial interference (paras 9–10).
- For High Courts: Deference to the tendering authority does not extend to applying a condition that is impossible to comply with (paras 9–10).
- For drafting tenders: Authorities should make clear that the original-submission requirement applies only to physical forms of bid security (para 8).
FAQs on E-Payment Bid Security in Government Tenders
1. What did the Supreme Court hold in Hardev Construction v. Union of India?
It held that rejecting a bid for not producing the original of bid security paid by e-payment was perverse, set aside the Patna High Court's order and directed that the appellant's financial bid be opened (paras 10–12).
2. Why could the appellant not produce an "original"?
Because the security was paid online and the money was already in the respondents' account; producing an original of an e-payment is an impossibility (paras 8, 10).
3. Why does the tender require originals at all?
For bank guarantees, demand drafts, FDRs and banker's cheques, no lien can be exercised unless the original reaches the authority, so a scanned copy is uploaded first and the original delivered later (para 8).
4. Does the Court not have to defer to the authority's reading of the tender?
Generally yes, but Prakash Asphaltings itself carves out an exception for mala fide and perverse understanding or application of tender terms, which applied here (paras 9–10).
5. What happens next in the tender?
The appellant must furnish bid security afresh within the stated time, after which its financial bid will be opened and considered along with the other bids under the tender conditions (para 12).
Keywords: 2026 INSC 1110, Hardev Construction v. Union of India, e-payment bid security, original bid security not required, tender rejection perverse, Clause 2.20.6 RFP, Railways EPC tender, Prakash Asphaltings distinguished, Supreme Court non-reportable judgment