Quick Answer: Penal time extension charges levied by NOIDA for the defaulting developer's delay cannot be imposed on home buyers and the Successful Resolution Applicant as CIRP costs. The Supreme Court held that NOIDA should waive these penalty charges in the peculiar facts of the case, set aside the NCLAT direction treating them as CIRP costs, and rejected NOIDA's claim for charges up to the 10th year.
In The Authorised Representative for Granite Gate Properties Pvt. Ltd., Ms. Rakesh Verma v. New Okhla Industrial Development Authority (2026 INSC 952), the Supreme Court held that time extension charges imposed by NOIDA as a penalty for the corporate debtor's delay cannot validly be mulcted on the home buyers and the Successful Resolution Applicant, and set aside the direction to treat them as CIRP costs (paras 14–16). A Bench of Justice J.B. Pardiwala and Justice K. Vinod Chandran allowed the home buyers' appeal and dismissed NOIDA's appeal seeking charges beyond three years up to the 10th year (paras 16–17).
Status: NCLAT direction treating time extension charges as CIRP costs set aside; Civil Appeal No. 3132 of 2026 allowed; NOIDA's Civil Appeal No. 4207 of 2026 dismissed (paras 16–17).
Headnote: Time Extension Charges and CIRP Costs
Insolvency and Bankruptcy Code, 2016 – CIRP costs – Real estate project – Home buyers as class of financial creditors – Successful Resolution Applicant – NOIDA lease deed – Time extension charges for delay in completion – Penal nature – UP Industrial Area Development Act, 1976 – Office orders dated 18.06.2015 and 18.10.2019 – Local authority's development purpose.
Held: (i) The purpose of NOIDA's lease is development of an urban and industrial township, including housing, and the authority, though in a commercial venture, cannot be divorced from its essential welfare purpose (paras 11–12).
(ii) Time extension charges are a percentage of the lease premium meant to penalise a defaulting developer and deter delay (para 14).
(iii) Where the defaulting developer is out of the picture and the project can be completed only through the Resolution Plan, the home buyers and the SRA cannot be penalised for the past sins of the corporate debtor (paras 14–15).
(iv) In the peculiar facts, NOIDA should waive the penalty charges; the direction to treat time extension charges as CIRP costs is set aside (paras 15–16).
(v) NOIDA's claim for time extension charges beyond three years up to the 10th year under the office order dated 18.10.2019 is rejected (para 16).
(paras 11–16)
Case Details: Granite Gate Properties (AR) v. NOIDA (2026 INSC 952)
Final Outcome: Home buyers' appeal allowed; direction to treat time extension charges as CIRP costs set aside; NOIDA's appeal dismissed.
Case: The Authorised Representative for Granite Gate Properties Private Limited, Ms. Rakesh Verma v. M/s New Okhla Industrial Development Authority and Ors.
Neutral Citation: 2026 INSC 952
Case No.: Civil Appeal No. 3132 of 2026 with Civil Appeal No. 4207 of 2026
Court: Supreme Court of India (Civil Appellate Jurisdiction) – Reportable
Date of Decision: 3 September 2026
Bench: Justice J.B. Pardiwala and Justice K. Vinod Chandran (author)
Relevant Acts & Sections: Insolvency and Bankruptcy Code, 2016 – CIRP costs; UP Industrial Area Development Act, 1976; Land Acquisition Act, 1894 (background); NOIDA office orders dated 18.06.2015 and 18.10.2019
Impugned Order: NCLAT order directing time extension charges under both lease deeds to be treated as CIRP costs for the maximum period of three years (para 6)
Counsel: Mr. Dhruv Mehta, Senior Advocate, for the Authorised Representative; Mr. Rachit Mittal for NOIDA; Mr. Krishnendu Datta, Senior Advocate, for the Successful Resolution Applicant (paras 7, 9, 10)
Source: Supreme Court of India (official website)
Key Holdings of the Supreme Court
- NOIDA's lease is for development of an urban and industrial township, including housing, and its welfare purpose cannot be ignored (paras 11–12).
- Time extension charges are penal in nature, designed to penalise a defaulting developer (para 14).
- Home buyers and the SRA cannot be penalised for the past sins of the corporate debtor (para 15).
- The NCLAT direction treating time extension charges as CIRP costs is set aside (para 16).
- NOIDA's claim for charges beyond three years up to the 10th year is rejected (para 16).
Brief Facts of the Case
The developer, M/s Granite Gate Properties Pvt. Ltd., took two plots on perpetual lease from NOIDA at a high premium and advertised two projects, "Lotus Boulevard" in Sector 100 and "Lotus Panache" in Sector 110 (para 2).
The developer was declared a corporate debtor. The Committee of Creditors consisted of home buyers as a class of financial creditors, and a Resolution Plan of M/s SMV Agencies Pvt. Ltd., now the SRA, was approved (paras 3–4).
The NCLAT directed that time extension charges under both lease deeds be treated as CIRP costs for the maximum period of three years. The home buyers' Authorised Representative appealed against this, while NOIDA appealed seeking charges beyond three years under the office order dated 18.10.2019 (paras 5–6).
During the CIRP, the home buyers pooled their own money to carry on construction under a "Pool and Build" mechanism, but NOIDA sealed three towers of Lotus Panache on 16.10.2024 pending a decision on the charges (para 7).
The project was to be completed in 2016, and a decade later the home buyers were still awaiting their homes (para 13).
Issues Before the Supreme Court
- Whether the time extension charges levied by NOIDA are to be treated as CIRP costs (para 11).
- Whether NOIDA could claim time extension charges beyond three years up to the 10th year under the office order dated 18.10.2019 (paras 6, 9, 16).
Court's Findings and Reasoning
Home buyers' case (paras 7–8): The AR argued that the charges were not incurred by the Resolution Professional, were penal in nature, related largely to the period before the insolvency commencement date of 10.01.2019, and that the home buyers could not be burdened with the developer's default.
NOIDA's case (para 9): NOIDA argued that the project could not continue without payment of the charges, and that under the office orders dated 18.06.2015 and 18.10.2019 the charges extend up to the 10th year and must be included as CIRP costs.
SRA's stand (para 10): The SRA adopted the AR's arguments and pointed out that the Resolution Plan caps contingent protection and provides that costs above Rs. 3 crore, unless adjudicated as CIRP costs, would first be recovered from allottees of towers 17/18/19 of Lotus Panache.
Purpose of the lease (paras 11–12): The land was acquired for developing an urban and industrial township. The original lease stipulated 4%, 5% and 6% charges for the first three years of delay, followed by cancellation. A local authority pursues welfare, not a mere profit motive.
Penalty cannot fall on home buyers (paras 13–15): The home buyers pooled money to continue the project and the CoC of home buyers approved the plan. The charges were meant to penalise the defaulting developer, who is now out of the picture; the essential purpose of development would fail if NOIDA insisted on default charges.
Final Outcome and Directions
- The penalty imposed by NOIDA on delay, sought to be mulcted on the SRA and home buyers, cannot be validly imposed in the peculiar facts of the case (para 16).
- The direction to treat time extension charges as CIRP costs is set aside and the impugned order modified to that extent (para 16).
- NOIDA's appeal for charges beyond three years up to the 10th year is rejected (para 16).
- Civil Appeal No. 3132 of 2026 allowed; Civil Appeal No. 4207 of 2026 dismissed (para 17).
Legal Principle Laid Down
Time extension charges levied by a development authority as a penalty for a developer's delay are meant to punish the defaulting developer. In the peculiar facts of a real estate CIRP, where the developer is out of the picture and home buyers and a resolution applicant are completing the project, such penalty charges cannot be imposed on them as CIRP costs, keeping in view the authority's essential development purpose.
Precedents Relied Upon
- The judgment does not rely on any reported precedent; the Court decided the issue on the terms of the lease deed, the NOIDA office orders and the peculiar facts of the case (paras 11–16).
Important Paragraphs of the Judgment
Verbatim extracts from the judgment. For the full text, refer to the judgment PDF below.
Para 1: "Yet another case highlighting the plight of home buyers, who invest their hard-earned life savings for a roof over their heads ..."
Para 12: "The authority surely is involved in a commercial venture, but it cannot be divorced from the essential purpose which every local authority pursues and advances, i.e.: welfare measures without a mere profit motive."
Para 13: "The essential purpose of development would fail if NOIDA brings in a stipulation of payment of default charges."
Para 15: "The homebuyers and the SRA are sought to be penalised for past sins of the Corporate Debtor, which cannot be allowed ..."
Para 16: "We set aside the directions to consider the time extension charges as CIRP costs and modify the impugned order to that extent."
Practical Impact of the Ruling
- For home buyers in insolvent projects: Penal time extension charges for the developer's default can be resisted when sought as CIRP costs (paras 14–16).
- For resolution applicants: The ruling removes a significant cost burden on completing stalled real estate projects (paras 14–15).
- For development authorities: Their welfare and development purpose weighs against insisting on penalty charges from home buyers (paras 12–13).
- For IBC practitioners: The decision rests on the "peculiar facts and circumstances", which should be borne in mind when citing it (para 16).
FAQs on Time Extension Charges in Real Estate CIRP
1. What did the Supreme Court hold in Granite Gate Properties (AR) v. NOIDA?
It held that NOIDA's penal time extension charges cannot be imposed on home buyers and the SRA, and set aside the direction treating them as CIRP costs (para 16).
2. Why were the charges not treated as CIRP costs?
Because they are a penalty for the defaulting developer, who is out of the picture, and the home buyers and SRA cannot be penalised for its past sins (paras 14–15).
3. What happened to NOIDA's claim up to the 10th year?
It was rejected, and NOIDA's appeal was dismissed (paras 16–17).
4. What role did NOIDA's purpose play?
The Court held that a local authority pursues welfare and development, not a mere profit motive, and development would fail if default charges were insisted upon (paras 12–13).
5. Is this a general rule for all projects?
The Court expressly decided it "in the peculiar facts and circumstances of the case" (para 16).
Keywords: 2026 INSC 952, Granite Gate Properties, Rakesh Verma, NOIDA, time extension charges, CIRP costs, home buyers, Successful Resolution Applicant, Lotus Panache, Lotus Boulevard, IBC real estate, Justice K. Vinod Chandran, Supreme Court reportable judgment