Quick Answer: A party to an arbitration does not lose the right to raise its own claims merely because it did not issue a separate notice under Section 21 of the Arbitration and Conciliation Act, 1996. Section 21 only fixes when arbitration commences for reckoning limitation. The Supreme Court set aside a Kerala High Court ruling that had confined the arbitration to the one dispute referred by the State, and restored the award of Rs. 1,99,90,777 in favour of the contractor in its entirety.
In M/s Bhagheeratha Engineering Ltd. v. State of Kerala (2026 INSC 4), the Supreme Court held that the High Court erred in holding that the Arbitral Tribunal was appointed only to decide dispute No. 1 and that the contractor's failure to issue a notice under Section 21 of the A&C Act for dispute Nos. 2 to 4 was fatal (para 14). The State's own conduct, in ignoring the contractual time-limits and seeking to have the Adjudicator's entire decision declared null and void, threw the whole dispute open before the Tribunal (paras 15, 18). A Bench of Justice J.B. Pardiwala and Justice K.V. Viswanathan allowed the contractor's appeal (para 22).
Status: Kerala High Court judgment dated 07.01.2025 in Arbitration Appeal No. 56/2012 set aside; arbitral award dated 29.06.2006 upheld in its entirety; appeal allowed with no order as to costs (para 22).
Headnote: Section 21 Notice and the Scope of Arbitral Claims
Arbitration and Conciliation Act, 1996 – Sections 2(9), 4, 16, 21, 23, 34 and 37 – Indian Contract Act, 1872 – Section 28(b) – Road maintenance contract – Multi-tier dispute clause (Engineer, Adjudicator, Arbitrator) – Arbitration invoked by employer on one dispute – Contractor's claims on other disputes – Absence of separate Section 21 notice – Conduct of employer – Widely worded arbitration clause – Claimant and counter-claimant – Award restored.
Held: (i) The sequence of events showed that the State's conduct precluded it from relying on Clauses 24, 24.1 and 25 of the General Conditions of Contract to contend that the contractor was foreclosed from raising the entire dispute before the Arbitrator (para 15).
(ii) The State itself invoked arbitration after the 28-day period, never treated the Adjudicator's decision as final and binding, withheld payment pending arbitration and sought a declaration that the Adjudicator's whole decision was null and void (para 15(b)–(e)).
(iii) Following M.K. Shah Engineers & Contractors v. State of M.P., the party at fault cannot be permitted to take advantage of its own wrong; the contention that the procedure for appointing the arbitrator was not complied with was rejected (para 15).
(iv) Section 21 is concerned only with determining when arbitration commences for reckoning limitation; there is no mandatory prerequisite of a Section 21 notice, and its absence is not fatal if the claim is otherwise valid and the disputes arbitrable (paras 16–17).
(v) Clause 25.3 was widely worded; the case was not governed by para 41(c) of State of Goa v. Praveen Enterprises, since the parties' conduct had thrown the entire dispute at large before the Tribunal (para 18).
(vi) Under Sections 2(9) and 23, once the Tribunal is constituted, claims, defence and counter-claims are filed; the contention that the contractor could not be a claimant for want of a Section 21 notice was completely untenable (paras 19–21).
(paras 14–22)
Case Details: Bhagheeratha Engineering Ltd. v. State of Kerala (2026 INSC 4)
Final Outcome: Civil Appeal allowed; High Court judgment set aside; arbitral award dated 29.06.2006 upheld in its entirety; no order as to costs.
Case: M/s Bhagheeratha Engineering Ltd. v. State of Kerala
Neutral Citation: 2026 INSC 4
Case No.: Civil Appeal No. 39 of 2026 (arising out of SLP (C) No. 7338 of 2025)
Court: Supreme Court of India (Civil Appellate Jurisdiction) – Reportable
Date of Decision: 5 January 2026
Bench: Justice J.B. Pardiwala and Justice K.V. Viswanathan (author)
Relevant Acts & Sections: Arbitration and Conciliation Act, 1996 – Sections 2(9), 4, 11, 16, 21, 23, 34 and 37; Indian Contract Act, 1872 – Section 28(b); General Conditions of Contract – Clauses 24.1, 25.1, 25.2 and 25.3
Impugned Order: Judgment dated 07.01.2025 of the Division Bench of the High Court of Kerala at Ernakulam in Arbitration Appeal No. 56/2012, upholding (on different grounds) the District Judge, Thiruvananthapuram's order in O.P. (Arb.) No. 238 of 2006 setting aside the award (paras 2–3, 5.19–5.20)
Counsel: Mr. Rajiv Shakdher, Senior Advocate, for the appellant; Mr. Naveen R. Nath, Senior Advocate, for the respondent-State (para 6)
Source: Supreme Court of India
Key Holdings of the Supreme Court
- The High Court erred in holding that the Tribunal was appointed only to decide dispute No. 1 and that it exceeded jurisdiction by deciding the entire dispute (para 14).
- The State, which itself disregarded the contractual time-limits and sought to annul the Adjudicator's entire decision, could not invoke those clauses against the contractor (para 15).
- A Section 21 notice is not a mandatory prerequisite to arbitration; it serves only to fix commencement for limitation (para 16).
- Non-inclusion of a dispute in the Section 21 notice does not bar a party from raising it if it falls within the arbitration agreement (paras 16–17).
- Under a widely worded arbitration clause, both sides may raise claims and counter-claims; para 41(c) of Praveen Enterprises did not apply (para 18).
- The party that first files its statement of claim is, for convenience, the claimant; lack of a Section 21 notice does not prevent a party from being a claimant (paras 19–20).
Brief Facts of the Case
The appellant was awarded four road maintenance contracts under the Kerala State Transport Project. The General Conditions of Contract provided for reference of the Engineer's decision to an Adjudicator within 14 days, and for reference of the Adjudicator's decision to arbitration within 28 days, failing which it would be final and binding (paras 5.1–5.5).
On 15.04.2004 the appellant approached the Adjudicator on four disputes. By decision dated 14.08.2004 the Adjudicator ruled for the appellant on dispute Nos. 1 and 3 and against it on dispute Nos. 2 and 4. The State did not pay, and on 01.10.2004 wrote that the decision on dispute No. 1 was not acceptable and appointed its arbitrator (paras 5.6–5.9).
The appellant objected that the reference was beyond 28 days. The State replied that the delay itself could be referred to the arbitrator and that payment would abide by the arbitration. On 29.11.2004 the appellant nominated its co-arbitrator, stating that if the Adjudicator's decision was reopened it would raise further issues (paras 5.11–5.14).
The Tribunal was constituted on 11.01.2005. The State sought a declaration that the Adjudicator's entire decision was null and void. By its Section 16 ruling, the Tribunal held the arbitration clause comprehensive and confined the appellant to the four disputes raised before the Adjudicator. By award dated 29.06.2006 it decided all four in the appellant's favour, awarding Rs. 1,99,90,777 with post-award interest at 18% (paras 5.15–5.18).
The District Judge set aside the award and restored the Adjudicator's decision. The High Court, though holding that the 28-day time-limit in Clause 25.2 offended Section 28(b) of the Contract Act, found the award invalid because only the State had issued a notice under Section 21, on one issue (paras 3, 5.19–5.20).
Issues Before the Supreme Court
- Whether the High Court was justified in holding that the Arbitral Tribunal was appointed at the State's request to adjudicate dispute No. 1 only (para 13).
- Whether the non-issuance of a notice under Section 21 of the A&C Act by the appellant was fatal to its claim before the Arbitrator (para 13).
Court's Findings and Reasoning
Conduct of the State (para 15): The Adjudicator was approached without any time-bar objection from the State; the Adjudicator's own decision came well after 28 days; the State's letter invoking arbitration came after 56 days; the State said the delay could itself be referred, disagreed with the decision, withheld payment pending arbitration, did not respond when the appellant said it would raise all issues, and asked the Tribunal to treat the entire decision as null and void. The State therefore never treated the Adjudicator's decision as final and binding.
Party at fault cannot benefit (para 15): Drawing support from M.K. Shah Engineers, where preceding steps to an arbitration clause were held capable of waiver and the party at fault was not allowed to set up their non-performance, the Court rejected the plea that the appointment procedure was not complied with.
Object of Section 21 (paras 16–17): Relying on ASF Buildtech v. Shapoorji Pallonji and Adavya Projects v. Vishal Structurals, the Court held that Section 21 is procedural, not jurisdictional, and only marks commencement for limitation. A claim not mentioned in the notice may still be raised if it falls within the arbitration agreement, and a respondent may raise counter-claims without a notice. Indian Oil Corporation v. Amritsar Gas Service reinforced this view.
Widely worded clause (para 18): Clause 25.3 covered any dispute arising out of or connected with the agreement. Under Praveen Enterprises, the claimant is not bound to the claims in the notice unless the agreement confines the arbitrator to specifically referred disputes. Since the parties' conduct had thrown the entire dispute at large, para 41(c) of that decision did not help the State.
Claimant and respondent (paras 19–21): Reading Sections 2(9) and 23, the Court noted that the party filing its claim first is conveniently called the claimant and the other may file a counter-claim; the State's argument that the appellant could never be a claimant was untenable. Iron & Steel Co. v. Tiwari Road Lines and MSK Projects v. State of Rajasthan did not apply, as there was no breach of appointment procedure and the Tribunal had not travelled beyond the reference. No other challenge to the merits of the award was canvassed.
Final Outcome and Directions
- Judgment of the High Court of Kerala dated 07.01.2025 in Arbitration Appeal No. 56/2012 set aside (para 22).
- Arbitral award dated 29.06.2006 upheld in its entirety (para 22).
- Appeal allowed; no order as to costs (para 22).
Legal Principle Laid Down
A notice under Section 21 of the Arbitration and Conciliation Act, 1996 only determines when arbitration commences for the purpose of limitation; it does not confine the Tribunal's jurisdiction. Where the arbitration clause is widely worded and the employer's own conduct has disregarded the pre-arbitral steps and reopened the earlier decision, the other party may raise its claims before the Tribunal even without issuing its own Section 21 notice, and the employer cannot rely on the unperformed pre-arbitral steps (paras 15–18, 20).
Precedents Relied Upon
- M.K. Shah Engineers & Contractors v. State of M.P., (1999) 2 SCC 594 – Relied upon – party at fault cannot set up non-performance of pre-arbitral steps. Discussed at para 15.
- ASF Buildtech Private Limited v. Shapoorji Pallonji & Company Private Limited, (2025) 9 SCC 76 – Relied upon – Section 21 is procedural, not jurisdictional. Discussed at para 16.
- Adavya Projects Private Limited v. Vishal Structurals Private Limited, (2025) 9 SCC 686 – Relied upon – disputes not in the Section 21 notice may still be raised. Discussed at para 16.
- Indian Oil Corporation Ltd. v. Amritsar Gas Service, (1991) 1 SCC 533 – Relied upon – counter-claim after reference of all disputes. Discussed at para 17.
- State of Goa v. Praveen Enterprises, (2012) 12 SCC 581 – Relied upon; para 41(c) held inapplicable – scope of claims and counter-claims under the arbitration agreement. Discussed at para 18.
- Iron & Steel Co. Ltd. v. Tiwari Road Lines, (2007) 5 SCC 703 and MSK Projects India (JV) Limited v. State of Rajasthan, (2011) 10 SCC 573 – Held inapplicable. Discussed at para 21.
Important Paragraphs of the Judgment
Verbatim extracts from the judgment. For the full text, refer to the judgment PDF below.
Para 14: "In our opinion, the High Court totally erred in setting aside the award on the basis that the appointment of the Tribunal was only to adjudicate dispute No.1."
Para 15: "We draw considerable support from the ratio of M.K. Shah (supra) on the aspect of conduct of the respondent and the holding therein, that the party at fault cannot be permitted to take advantage of the same."
Para 16: "Section 21 is concerned only with determining the commencement of the dispute for the purpose of reckoning limitation. There is no mandatory prerequisite for issuance of a Section 21 notice prior to the commencement of Arbitration."
Para 16: "Failure to issue a Section 21 notice would not be fatal to a party in Arbitration if the claim is otherwise valid and the disputes arbitrable."
Para 18: "In the present case, we have already held that the rigors of clause 24, 24.1 and 25 have not been followed by the parties and by their conduct the entire dispute have been thrown at large before the Arbitral Tribunal."
Para 20: "Hence, to contend that the appellant cannot be referred to as a claimant because no notice under Section 21 has been issued is completely untenable."
Practical Impact of the Ruling
- For contractors: Once the employer invokes arbitration under a broad clause, the contractor can raise its own claims without issuing a separate Section 21 notice; the notice matters for limitation, not jurisdiction (paras 16, 20).
- For government employers: An employer that ignores pre-arbitral time-limits and seeks to reopen an adjudicator's decision cannot later confine the arbitration to its own chosen issue (para 15).
- For drafting dispute clauses: Only where the agreement confines the arbitrator to specifically referred disputes will the reference control the jurisdiction (para 18).
- For courts under Sections 34 and 37: An award cannot be set aside on the footing that the successful party issued no Section 21 notice of its own (paras 14, 16, 22).
FAQs on Section 21 Notice and Arbitral Claims
1. What did the Supreme Court decide in Bhagheeratha Engineering Ltd. v. State of Kerala?
It set aside the Kerala High Court's judgment and upheld in its entirety the arbitral award dated 29.06.2006 in favour of the contractor (para 22).
2. Is a Section 21 notice mandatory before raising a claim in arbitration?
No. Section 21 only determines when arbitration commences for reckoning limitation, and failure to issue it is not fatal if the claim is otherwise valid and arbitrable (para 16).
3. Why could the State not confine the arbitration to dispute No. 1?
Its own conduct, including invoking arbitration late, withholding payment and asking the Tribunal to declare the Adjudicator's whole decision null and void, threw the entire dispute open (paras 15, 18).
4. Can a party that did not invoke arbitration be the claimant?
Yes. The party that files its statement of claim first is, for convenience, called the claimant; the absence of a Section 21 notice does not prevent this (para 20).
5. When does a reference restrict the arbitrator's jurisdiction?
When the arbitration agreement requires specific disputes to be referred and confines the arbitrator to them, as in para 41(c) of Praveen Enterprises; that was not this case (para 18).
Keywords: 2026 INSC 4, Bhagheeratha Engineering Ltd. v. State of Kerala, Section 21 Arbitration and Conciliation Act, notice of invocation, commencement of arbitration, limitation, counter-claim, Section 23, Section 2(9), multi-tier dispute resolution clause, adjudicator decision, Section 28(b) Contract Act, Praveen Enterprises, ASF Buildtech, M.K. Shah Engineers, Kerala State Transport Project, Justice K.V. Viswanathan, Justice J.B. Pardiwala, Supreme Court judgment
Related on LegalTaxGuru
Download Judgment PDF – Bhagheeratha Engineering v. State of Kerala
Judgment PDF: 2026 INSC 4 – M/s Bhagheeratha Engineering Ltd. v. State of Kerala (Civil Appeal No. 39 of 2026) – Download Judgment PDF
Source: Supreme Court of India (official website).